Construction zone updates - 2020 March

Fortnightly Construction Update - 26 March

Fortnightly Construction Update - 26 March

The first of the concrete for Level 3 (Operating Theatres) has been poured and work has begun on the exterior walls for the ground level of the hospital tower.

View PDF  
Posted 26 Mar 2020
Fortnightly Construction Update - 12 March 2020

Fortnightly Construction Update - 12 March 2020

A second tower crane will be erected this weekend (weather permitting) near the existing childcare centre.

View PDF  
Posted 12 Mar 2020